Dry Wall

This has been an exciting week for the project. The week started with painting the rafters black.

UNADJUSTEDNONRAW thumb 3239UNADJUSTEDNONRAW thumb 3238

The electrical and plumbing was completed and inspected so they could start hanging dry wall.

Here are the upstairs master bath, half bath, and closet areas.

UNADJUSTEDNONRAW thumb 3257UNADJUSTEDNONRAW thumb 324d

The door to the closet.(The former dark room door when the building was a photography studio in the 60’s as far as we know.)

UNADJUSTEDNONRAW thumb 3259

The downstairs bathrooms and janitors closet areas.

UNADJUSTEDNONRAW thumb 325c

And our garage area in the back of the building.

UNADJUSTEDNONRAW thumb 326e

And finally they poured the concrete next to the Otis Material Lift. 

UNADJUSTEDNONRAW thumb 3263

This upcoming week will be the remaining dry wall, electrical and plumbing finish outs, and the hanging of the lighting fixtures.

Getting Closer

We are getting closer. They finished painting the front and west sides of the building.UNADJUSTEDNONRAW thumb 3219UNADJUSTEDNONRAW thumb 3229

They started framing of the 2nd floor windows. When we installed the new windows they temporary installed them to dry in the building. Now they are finishing the installation.

UNADJUSTEDNONRAW thumb 3221

HVAC continues downstairs.

UNADJUSTEDNONRAW thumb 3223UNADJUSTEDNONRAW thumb 3217

And we started to seal the upstairs brick in the shower area.

BeforeUNADJUSTEDNONRAW thumb 320e

AfterUNADJUSTEDNONRAW thumb 3220UNADJUSTEDNONRAW thumb 3222

Finally framing is almost complete. Here is the rotating door to the closet. We salvaged it from the building when there was a photography business upstairs and they had a dark room door.

UNADJUSTEDNONRAW thumb 3228

Framing Continued

We have the start of walls upstairs. They have started framing out the bathroom, 1/2 bath, mechanical room, and the closet worthy of a queen:)

UNADJUSTEDNONRAW thumb 2ec1

This is the closet area. When it’s done, it will be 16 x 17 and have a round couch in the middle with a large chandelier above it.

UNADJUSTEDNONRAW thumb 2ec3

The shower area and Master Bath area. The shower will be all glass with the brick wall on one side.

UNADJUSTEDNONRAW thumb 2ec5

The picture below shows the overall size of everything. These are going to be the only walls.Everything else will be wide open. The windows on the right side will be opened to bring in a lot of more natural lighting. If you look closely you can see the plumbing on the right where our kitchen island will be.

UNADJUSTEDNONRAW thumb 2ec6

And finally looking forward.Things are coming along! This shows the 1/2 bath and mechanical room entrance.

UNADJUSTEDNONRAW thumb 2ebf

Framing

Our contractor has started the framing downstairs and the plumbing rough in upstairs.

Downstairs we will have two ADA bathrooms, a mechanical room, and a small janitor’s closet.

UNADJUSTEDNONRAW thumb 2e97

UNADJUSTEDNONRAW thumb 2e8b

To comply with the fire codes, we had to rearrange the stairs.  Now they are brand new, safe, and they look amazing. 

UNADJUSTEDNONRAW thumb 2e9b

UNADJUSTEDNONRAW thumb 2e8f

Upstairs they have reinforced the joists and are starting to install the subfloor.  In addition, they are roughing in the plumbing.

UNADJUSTEDNONRAW thumb 2e8e

UNADJUSTEDNONRAW thumb 2e6d

UNADJUSTEDNONRAW thumb 2e9a

And we have been collecting our faucets, sinks, and lights.  For our Master Bath we found this ‘vanity’ at Consignment Heaven in Dallas. It is really a side board/buffet for a formal dining room.  Now it will have a new life as our vanity.  The sink vessels on top came from Wayfair.com and we just ordered the faucets from Amazon. It should be spectacular once it’s all installed!!!!

UNADJUSTEDNONRAW thumb 2e59

Most of the power in the building has been disconnected. We decided we needed more light to work on all of our small DIY projects, and it finally dawned on us that if we cleaned the row of windows at the top of the storefront, we would have a lot more natural light.  

So, we hauled out the ladders and scrapers, and went to work.  Unfortunately, one of the previous owners decided to paint all of the windows with primer.  Note to self: Primer does NOT come off glass easily.  If you ever have a project where you need to strip paint, I really recommend a product called Ready Strip.  It works, you don’t have to wear gloves, and it doesn’t smell bad.  We slapped some of that stuff on the windows, and somehow we managed to clean the paint off the top windows on one side (pic below).  We are going to hold off removing the remaining paint until everything is complete and we are ready to show the building to the general public.

UNADJUSTEDNONRAW thumb 2e9d

UNADJUSTEDNONRAW thumb 2e89

Lastly, Happy Memorial Day from Cleburne TX!!!!

UNADJUSTEDNONRAW thumb 2e57